DL M&E were entrusted as the preferred partner to complete a full refurbishment for Wates Smartspace office in Warrington. Covering 6,600 sq. ft. over two floors, the project emphasised wellbeing and sustainability. Leveraging our experience in meeting Wates Smartspace high standards, we successfully completed the refurbishment within an 8-week timeline, ensuring the space was ready for staff occupancy.
The Sustainability aim for the project was to achieve an Energy Performance Certificate (EPC) rating of A+, which our team worked with other contractors to achieve the sustainability target.
The office fitout prioritised workplace wellbeing, incorporating dedicated spaces such as:
Mechanical and plumbing installation works included installation of air conditioning , ventilation systems to all areas. As well as plumbing works to new tea point areas and WC.
Key installations included:
Electrical works included a full strip-out of small power, lighting, fire alarm, and data systems across both floors, while retaining and re-using certain elements where possible.
Key electrical works included:
All works were successfully completed within the required 8-week timeframe, allowing staff to transition seamlessly into their modern, sustainable and efficient workspaces.