National Bank, Keens House

Cat B MEP Refurbishment
No items found.
View full size image gallery
DL M&E were engaged by a longstanding corporate banking framework partner, following their recent acquisition of new premises in Andover. The project involved an extensive Cat B modification project with the primary goal of aligning the MEP systems of the Tech Rooms with the client's MEP standards while enhancing the overall workspace holistically.

Key Project Initiatives:

  • Implementation of new split air conditioning systems within tech rooms on an N+1 basis, complete with drip trays and water leak detection.
  • Introduction of new Mitsubishi heat recovery systems in the main area for efficient supply and extraction of conditioned air.
  • Installation of new extract systems.
  • Creation of new Changing Places and Shower Rooms.
  • Repurposing of existing locker room into a modern breakout room with a new kitchenette, providing a versatile and collaborative workspace.
  • Comprehensive upgrade of both male and female WC areas, incorporating new sanitaryware, fixtures, and fittings to elevate sustainability and user experience.
  • Installation of a dedicated distribution system to ensure generator backed resilience for the upgraded air conditioning equipment, guaranteeing continuous operation during power outages.
  • Installation of new power distribution by means of new power poles within work areas.

The project was undertaken in a live environment, demanding meticulous coordination across various installations to minimize disruptions to ongoing operations. Effective communication and a well-coordinated schedule were paramount in overcoming these challenges and ensuring the seamless execution of the modifications.

The project successfully transformed Keens House into a modern, user-friendly workspace. Not only did it enhance the overall aesthetics and functionality, but it also provided critical resilience for the IT infrastructure, meeting the client's comprehensive design standards.

DL M&E earned outstanding praise from the client's consultancy team, citing the exceptional quality of the MEP installation, and commending the proficiency of the delivery team.

Client
National Bank
Services
M&E CAT B Fit Out
Sector
Banking
£
Value
£500k - £1m
Contract Length